Editor’s Note — Correction (June 20, 2026): An earlier version of this article stated that “the Town of Beloit board agreed to reimburse Cambrin up to $175,000 for preliminary work via a TIF arrangement.” This was incorrect. Per the pre-development agreement signed July 15, 2025, it is Cambrin LLC that agreed to reimburse the Town of Beloit up to $175,000 for costs the Town incurs related to the project. Additionally, TIF is a separate financing mechanism under future negotiation — it is not the vehicle for the $175,000 cost recovery. We regret the error.

ROCK COUNTY, WI — Three different data centers are now in active discussion in Rock County. Combined investment, if all three move forward: more than $9 billion. Combined power demand: more than 1 gigawatt — roughly the output of a mid-sized power plant. And on November 3, Janesville voters will get a chance to require their own approval before the largest of them can break ground.

The story is moving fast, the players are spread across at least five different press releases, and the official information has been thin on purpose — multiple Wisconsin communities have signed nondisclosure agreements before public announcements. Here’s the full picture, drawn together from reporting by The Janesville Gazette, MyStateline, Wisconsin Watch, the Wisconsin Newspaper Association, Wisconsin Public Radio, and Ballotpedia.

1. The big one: $8 billion on the old GM plant

The largest Rock County proposal — and the only one with formal city action so far — targets the 250-acre site of the former General Motors assembly plant along South Jackson Street, the same plant that shut down in 2008 and put 7,000 people out of work in waves through the 1980s and 90s.

  • Developer: Viridian Acquisitions LLC, a Colorado-based firm specializing in brownfield redevelopment
  • Total investment: Over $8 billion
  • Configuration: Either an 11-building data center campus or an 8-building hyperscale campus
  • Power requirement: Up to 800 megawatts — a number that reads like science fiction; for context, that’s the demand of a small city
  • Site cleanup: $30 million brownfield remediation under a DNR-approved plan; the property has been the subject of multiple failed redevelopment proposals over the years
  • Estimated jobs: 1,200 construction; 600 permanent operational
  • Estimated state economic impact: $2.05 billion direct

The Janesville City Council voted 5-2 on November 10, 2025 to approve a Letter of Intent with Viridian, kicking off a 120-day negotiation period. Council member Heather Miller cast one of the two no votes, citing the absence of public health input in the process.

Public response was loud. More than 20 residents spoke against the proposal at the council meeting, raising concerns about water and power demand on the local grid, public health risks for nearby neighborhoods, and broader distrust of the corporate accountability framework around hyperscale data centers.

2. The newer one: Town of Janesville farmland

The second proposal is younger, smaller-scale, and physically separate. In April 2026, the Town of Janesville (a separate jurisdiction from the City of Janesville) received a letter from an undisclosed tech company proposing a data center at the corner of North Polzin Road and West Fenric Road — currently farmland, with dozens of homes nearby.

Town Planning Committee Chairman Doug Rebout has emphasized that “the town and a data center developer have made no formal decisions.” State Rep. Ann Roe, whose district covers part of Rock County, told constituents the project is still in early phases — potentially six months out from major decisions.

The infrastructure cast around this one is interesting. Reportedly involved or in feasibility discussions:

  • Rock Energy Cooperative and Alliant Energy — potential power providers
  • American Transmission Company — conducting a feasibility study, almost certainly because the site sits near major transmission lines
  • IGNIS Energy — a Houston-based geothermal company in preliminary discussions, suggesting some of the cooling/power architecture may not be conventional grid-only

Two community groups have organized in opposition: No Janesville Data Center and Rock County Neighbors for Responsible Development. Their core argument is consistent with similar opposition groups across the state: that hyperscale data centers “take more from a community than they give back” — significant power and water demand, modest permanent employment, often substantial tax abatements.

3. The third one: Meta in the Town of Beloit

The third Rock County proposal involves Meta (parent company of Facebook and Instagram) and a private quarry owner in the Town of Beloit. Public details remain limited — a Delaware-based entity called Cambrin LLC signed a predevelopment agreement in July 2025 and was announced in March 2026.

The Town of Beloit board agreed to reimburse Cambrin up to $175,000 for preliminary work via a TIF (tax increment financing) arrangement. Public records have raised transparency concerns: town board minutes from May 2024 reference negotiations being approved — without explicitly mentioning that the project under negotiation was a data center.

That kind of pre-disclosure secrecy isn’t unique to Beloit. Wisconsin Watch has confirmed data center NDAs were signed by multiple communities before public announcements, including Beloit (February 2025), Rock County (January 2025), Janesville, and Menomonie.

4. The November 3 ballot initiative

This is where Janesville voters get the formal say. The community group No Janesville Data Center ran a successful petition drive: they needed 3,915 signatures (15% of votes cast in the most recent gubernatorial election); they got 3,927 certified as of January 21, 2026.

The measure on the November 3, 2026 ballot would require voter approval at a general or special election before any development project exceeding $450 million can be built on undeveloped portions of the GM/JATCO site. The $450 million threshold is well below the $8 billion Viridian project — meaning if the measure passes, the Council’s 5-2 Letter of Intent is not the final word. Voters would need to approve the actual development.

This isn’t the first such measure in Wisconsin. Port Washington passed a similar referendum in April 2026 requiring voter approval for TIF districts over $10 million — reportedly the first data center referendum in U.S. history.

5. The Wisconsin context — this is happening everywhere

Rock County’s three proposals are part of a much larger statewide pattern. Confirmed Wisconsin data center developments now include:

  • Mount Pleasant (Racine County): Microsoft, under construction, on the original Foxconn site
  • Port Washington (Ozaukee County): Vantage/OpenAI/Oracle “Lighthouse” campus, $15 billion, broke ground December 2024 — police were called approximately 12 times during early construction; voters then passed referendum requiring approval for large TIFs
  • Beaver Dam (Dodge County): Meta, $1 billion first facility plus $40 million second, both approved 2026
  • Janesville City: $8 billion Viridian (the GM site)
  • Town of Janesville: Undisclosed company on Polzin/Fenric farmland
  • Town of Beloit: Cambrin/Meta on the quarry site
  • Grant County (Cassville/Waterloo): $1 billion proposal in site selection
  • DeForest: QTS Data Centers (Virginia-based) had a $12 billion project announced — cancelled in January 2026 after community opposition, ultimately relocated to Iowa

Statewide voter sentiment is striking. Two independent February 2026 polls — from Wisconsin Conservation Voters and Marquette Law School — both found that 70% of registered Wisconsin voters believe data center costs outweigh benefits. An earlier Marquette poll showed opposition at roughly 70%+ across every level of how-much-have-you-heard about data centers, suggesting opposition isn’t about misinformation — it’s consistent across knowledge levels.

6. The fight that’s not on the ballot: who pays for the power

The under-reported half of the data-center conversation is the rate-structure fight at the Public Service Commission. The core question: when an 800-megawatt facility plugs into a grid that wasn’t built for it, who pays for the upgrades — the data center, or every other ratepayer in the utility’s service area?

The PSC approved an Alliant Energy-Meta deal in May 2026 but criticized what it called the “black box approach” in how the rate was structured. Wisconsin ratepayers are already on the hook for an estimated $1 billion in stranded-asset debt from old shuttered power plants — the concern is that a rush to build new generation for data centers could create another similar stranded-asset risk down the line.

The 2025-26 Wisconsin legislative session ended without passing any of the data center bills under consideration: NDA prohibitions, ratepayer protection legislation, stranded-asset accountability rules. Assembly Speaker Robin Vos called requiring data centers to fund their own electricity “probably an 80% issue for the public.” The next legislative session begins January 2027 — after the November vote.

What to watch next

  • Now through November 3: Campaigning around the Janesville ballot initiative. Expect significant outside spending on both sides. Watch the Wisconsin Conservation Voters and No Janesville Data Center groups for opposition messaging; expect business-association ads supporting the development.
  • Spring – Summer 2026: The Town of Janesville Polzin/Fenric proposal will move out of preliminary discussions. Watch for an American Transmission Company feasibility study release.
  • Public Service Commission: Ongoing rate-structure decisions for We Energies (Mount Pleasant/Port Washington) and Alliant Energy (Meta facilities) will set precedents that affect any Janesville deal.
  • January 2027: Next Wisconsin legislative session opens. NDA ban bills, ratepayer protection bills, and stranded-asset accountability bills are all expected to return.

How to follow developments locally

  • City of Janesville publishes data center insights at janesvillewi.gov
  • No Janesville Data Center is the petition group; they’re the most likely source for opposition messaging and ballot information
  • 608 Scanner’s daily briefing covers Rock County overnight scanner activity plus the day’s press releases — free signup here
  • Wisconsin Watch has the most thorough investigative reporting on the statewide data center build-out: wisconsinwatch.org
  • Public Service Commission filings on rate cases are public: psc.wi.gov

Have a correction or a tip we missed?
Email 608areascanner@gmail.com. We update articles when verified new information comes in.

Sources: The Janesville Gazette / Wisconsin Newspaper Association (May 2026), MyStateline (WTVO), Wisconsin Public Radio, Wisconsin Watch, Ballotpedia, Marquette Law School poll, Wisconsin Conservation Voters poll. All facts in this article are drawn from public reporting and official government sources. No NDAs, no insider tips, no speculation beyond what’s been published.

Last updated: May 9, 2026.